Payment and performance bonds, often called P&P bonds, are two surety bonds a general contractor furnishes so that a third party, the surety, stands behind the contract. The performance bond covers the owner if the contractor fails to finish the work as the contract requires. The payment bond covers the subcontractors and suppliers if the contractor fails to pay them. On public projects across the Southeast, state law requires both bonds once a contract crosses a set dollar amount, and no work starts until they are in place. On private projects they are optional, which is exactly why owners need to decide early if they want them.
How a Surety Bond Works
A construction bond involves three parties. The principal is the contractor who buys the bond. The obligee is the owner the bond protects. The surety is the bonding company that guarantees the contractor’s obligations. Unlike insurance, a bond is not designed to absorb losses. If the surety pays a claim, the contractor owes the surety that money back under an indemnity agreement, often backed by the company and its owners personally.
That is why bonding is also a screening tool. Before writing a bond, the surety reviews the contractor’s financial statements, work in progress, backlog, and track record. A contractor who can bond a project has passed an outside review that an owner could not easily do alone.
Performance Bond vs. Payment Bond
What the Performance Bond Covers
The performance bond is written in favor of the owner, usually for 100 percent of the contract price. If the contractor defaults and the owner properly terminates, the surety has several options under most bond forms. It can finance the original contractor to finish, bring in a replacement contractor, take over the work itself, or pay the owner up to the bond amount. Owners need to follow the notice and termination steps in the bond exactly, because skipping them can weaken the claim.
What the Payment Bond Covers
The payment bond is written for the benefit of the subcontractors, suppliers, and laborers on the project. Public property generally cannot be liened, so on public work the payment bond takes the place of lien rights. On private work, a payment bond gives unpaid trades a claim against the bond, which helps keep liens off the owner’s property and keeps the job moving when a payment dispute comes up. Claimants have to meet strict notice and filing deadlines, which vary by state.
Bond Requirements on Public Projects in the Southeast
The federal Miller Act requires P&P bonds on federal construction contracts, and each state has its own version, usually called a Little Miller Act, for state and local public work. The thresholds below come from each state’s statute and apply to typical public building contracts. Highway work, state agencies, and individual owners can follow different rules, so the bid documents always control.
| State | When bonds are required | Notes |
|---|---|---|
| Georgia | Local government public works contracts estimated over $100,000 (O.C.G.A. §§ 36-91-70 and 36-91-90) | Owners may require bonds on smaller contracts |
| Florida | Contracts for public buildings and public work (Fla. Stat. § 255.05) | State work of $100,000 or less is exempt, and local governments may waive bonds at $200,000 or less |
| North Carolina | Each contract over $50,000 on a project totaling over $300,000 (N.C.G.S. § 44A-26) | Both bonds at 100 percent of the contract amount |
| South Carolina | State construction contracts (S.C. Code § 11-35-3030) | Bonds can be waived on contracts of $50,000 or less |
| Tennessee | Public works contracts over $100,000 (Tenn. Code § 12-4-201) | Statutory payment bond minimum is 25 percent, and many owners require 100 percent P&P bonds |
| Alabama | Public works contracts of $50,000 or more (Ala. Code § 39-1-1) | Performance bond at 100 percent and payment bond at no less than 50 percent |
Schools, municipal buildings, public safety facilities, and other institutional and municipal projects almost always land above these thresholds, so bonding is part of every bid. Bonding is often paired with a bid bond at the proposal stage, and the requirements show up in the bid package along with the RFP or RFQ documents.
Should Private Owners Require P&P Bonds?
On a private project, the owner decides. The case for bonds is strongest when the project is large compared with the contractor’s size, when a lender requires them, when the schedule cannot absorb a contractor failure, or when the owner has no prior history with the contractor. Developers financing hotels and ground-up commercial buildings often see bond requirements written into their loan terms.
The bond premium is usually included in the contractor’s price as a line item, and it rises when the contract value increases through change orders. On a guaranteed maximum price contract, the bond is typically written for the GMP amount. Owners who want bonds should say so before pricing, because adding them after the contract is signed means reopening the price.
When a Bond Claim Happens
Performance bond claims usually follow a documented default: missed milestones, abandoned work, or failure to correct defective work after notice. The owner notifies the contractor and the surety, holds a conference if the bond form calls for one, and formally terminates before demanding that the surety act. Payment bond claims start with the unpaid sub or supplier giving notice within the statutory window, and many states require the lawsuit to be filed within a year of the last work or of project completion. Bond claims on both sides are slow and costly, which is why owners get the most value from a bond by choosing a contractor unlikely to need it.
Bonding Starts With the Right Contractor
A bond guarantees the contract, but it cannot make up for a contractor who is stretched thin, underbid the job, or does not understand the owner’s requirements. The surety’s review helps screen those risks, and so does looking at how a contractor plans, prices, and closes out work before the bond is ever needed.
Stonehenge Construction Services builds institutional, municipal, hospitality, and commercial projects across Georgia and the Southeast. If your project requires payment and performance bonds, or you are deciding if a private project should, our commercial contracting team can walk through the bid requirements, bonding, and closeout terms with you before pricing begins.
Frequently Asked Questions
What is a P&P bond?
A P&P bond is a payment and performance bond package. The performance bond guarantees the contractor will complete the work, and the payment bond guarantees the contractor will pay its subcontractors and suppliers.
What is the difference between a performance bond and a payment bond?
The performance bond protects the owner against the contractor failing to finish the work. The payment bond protects subcontractors, suppliers, and laborers against the contractor failing to pay them.
Who pays for payment and performance bonds?
The contractor buys the bonds from a surety, and the premium is normally built into the contract price, so the owner pays for it indirectly.
Are P&P bonds required on private projects?
Not by state law. Private owners and their lenders decide if they want them, and the requirement should be in the bid documents before pricing.